HUMAN CREMATION CASE STUDIES
Woodland Cemetery in Sweden
Matthews built and installed a four-incinerator facility at Woodland Cemetery in Stockholm with a flue gas cleaning system. Featuring 1.1m front doors, rear-side ash discharge, an integrated ash cooling system, and an automatic coffin loader, these cremators are capable of 24-hour operation, and are used for 6-7 cremations daily. The system features a unique flue gas chimney booster, as well as a water-cooled circuit for heating and cooling the building. The facility was completed in 2012 and is compliant with all relevant European environmental regulations.
INSTALLATION
- Sweden, Stockholm – Woodland Cemetery Listed as Unesco World Heritage
CREMATIONS PER DAY
- 6-7 Cremations, per day each CRM unit
EMISSIONS
- In compliance with the European Standards and Regulations in the country of installation.
SCOPE OF PROJECT
- CRM 6R
- High-performance cremator = H24 working process
- Front door opening = 1100mm
- Ash discharge = rear-side
- Integrated ash cooling system
- Automatic coffin insertion system with lifting truck
- Flue gas cleaning with reagent injection system
- Water circuit for heating and cooling building
- Unique booster solution for flue gas chimney 250 meters far away from cremators building